The Arithmetic of Approval: Why Every Brief Should State How Many Choices It Requires

Simon Levy
The Arithmetic of Approval: Why Every Brief Should State How Many Choices It Requires

Photo: Raimond Spekking, CC BY-SA 4.0, via Wikimedia Commons

A consultancy proposal is expected to be precise about cost, duration and deliverables. It will usually name the team, describe the method and set out the assumptions on which the fee depends. It is rarely precise about the one resource the client must supply in kind: the capacity to make decisions. That omission is not dishonest, but it is expensive. A project can be fully scoped and still fail because the client was asked to approve more choices than its governance could absorb.

The answer is not a longer proposal. It is a clearer one. Before work begins, both sides should agree a decision allowance: a practical estimate of how many client decisions the project will require, who will make them, and by when. The purpose is not to limit ambition. It is to make the client's side of the bargain visible while there is still time to adjust it.

Deliverables are not the same as decisions

A scope document counts what the supplier will produce. It does not count what the client must choose. One line item — “design sign-off” — may conceal six separate decisions about audience, tone, format, channels, timing and budget. A single steering group meeting may be asked to ratify a direction, select an option and approve a change of supplier. The paperwork looks modest; the cognitive and political load is not.

This matters because decision-making is work. It consumes senior attention, requires preparation and often depends on people who are already fully committed. In UK owner-managed firms, the same two or three individuals may sit on every approval forum. In larger organisations, delegated authority may be clear on paper but slow in practice. A project that adds twelve decision points to an already crowded calendar is not simply adding twelve agenda items. It is adding twelve opportunities for delay.

Count the events, not the documents

The first discipline is to stop counting documents and start counting decision events. A decision event is any moment at which the client must choose between credible alternatives, authorise a commitment, or accept a trade-off. It may take place in a workshop, a board paper, an email chain or a formal sign-off. What matters is that someone with authority must exercise judgement.

A useful estimate can be built from the project plan. For each workstream, ask four questions. What choices will the client be asked to make? Who owns each choice? What evidence will they need? And which forum will record it? The answers need not be perfect. An approximate count, agreed in good faith, is far better than an unspoken assumption that the client will simply “be available”.

Three limits are worth setting. The first is a count: the maximum number of decision events the client will be asked to handle in a given period. The second is a concentration limit: no single individual should own more than a stated share of the decisions, lest the project depend on one diary. The third is a calendar limit: decision windows should be scheduled before the work that depends on them, not after.

A one-page canvas for kick-off

A decision allowance does not need a lengthy methodology. It needs a single page, completed jointly at kick-off and revisited at each major stage. The canvas should record:

Field What it captures
Decision event The specific choice to be made, expressed as a question
Client owner The named individual with authority to decide
Authority level Whether the owner can decide alone or must escalate
Evidence required The minimum information needed for a good decision
Decision forum The meeting, paper or written process that will record it
Window The dates between which the decision must be taken
Fallback What happens if the window is missed
Allowance The agreed maximum number of such events in the period

The canvas is not a contract in the legal sense. It is a planning instrument. Its value lies in the conversation it forces: who will actually decide, what they will need, and how many choices the project is asking of them. When the allowance is exceeded, both sides can see it early and choose between extending the timetable, delegating authority or reducing scope. That is a far better position than discovering the overload three weeks before delivery.

Signs that a brief is over-asking

Some briefs quietly request more decisions than the client has capacity to make. The warning signs are consistent. The same senior person appears as owner for every decision. Workshops are scheduled without a stated choice to be made. “Sign-off” is used as a synonym for “review”. The project plan contains review points but no decision points. Or the client has not identified who can approve a change without referring upwards.

These are not reasons to refuse the work. They are reasons to renegotiate the decision allowance before the fee is fixed. A supplier that surfaces the issue early is not being difficult; it is protecting the client from a project that looks well governed but is quietly unable to decide.

A cap is a form of honesty

A decision allowance is sometimes mistaken for rigidity. It is the opposite. It acknowledges that client attention is finite and that good decisions take preparation. By putting a number on the choices a project requires, it makes the implicit explicit. It gives the client a basis for delegating, the supplier a basis for planning, and both parties a shared language for re-planning when reality intervenes.

Scope the work, by all means. Scope the team and the fee. But scope the decisions too. A brief that states how many choices it requires is not doubt. It is arithmetic — and arithmetic agreed at the start is cheaper than arithmetic discovered at the end.

All Articles

Related Articles

The Unpriced Door: Costing Reversibility in UK Consultancy Proposals

The Unpriced Door: Costing Reversibility in UK Consultancy Proposals

The Adoption Ledger: Auditing the Quarter After the Adviser Leaves

The Adoption Ledger: Auditing the Quarter After the Adviser Leaves

Agreeing the Rules of Engagement: The Commercial Weight of a Kick-Off Meeting

Agreeing the Rules of Engagement: The Commercial Weight of a Kick-Off Meeting